The news
Malaysia is preparing a new law for data centres. Trade and industry minister “Johari Abdul Ghani” announced it on 12 November. Data centres must report their power use and how many graphics chips (GPUs) they import. These chips are the main hardware for AI. Operators’ names and each centre’s location must also be known. The stated aim is that the chips are not sent elsewhere. The law is still a draft.
How data centres could hurt the Earth despite Malaysia’s data centre law
- Certain: In September 2026 the “Energy Commission” said data centres use 9.28% of Malaysia’s electricity. Heat pushes this up, because cooling needs more power.
- Probable: The energy ministry forecasts that the data-centre share of power in western Malaysia will rise. The share goes from 7% in 2026 to 31% in 2035. Yearly use climbs from 10,544 to 73,274 gigawatt-hours, nearly seven times more.
- Certain: Gas makes up about 55% of the country’s power-plant capacity. Economy minister “Akmal Nasrullah” says Malaysia must add 9 gigawatts of gas plants by 2032. The reason is growing power demand.
How Malaysia’s data centre law could help the Earth
- Certain: Reserved capacity that goes unused is billed too. “Johari” gave this example: a data centre reserves 100 megawatts and uses 50. The other 50 are billed too. His aim is to cut reservations that may be used one to three years later.
- Certain: Of 117 approved data-centre projects, 55 have started work. “Johari” says monitoring must continue after approval.
- Our estimate: In August 2026, data centres in western Malaysia had contracted 2,346 megawatts of power. They were drawing only 1,374 megawatts. The gap is about 970 megawatts. If that ran at full power for a year, it would need about 8,500 gigawatt-hours. That is about 80% of the forecast use for 2026, which is 10,544 gigawatt-hours. The grid has set this capacity aside for them. If half of it is never used, who pays for the extra power plant?
Our conclusion
For the Earth, the new path is better than booking power with no account. But the stated aim of the law is not to cut power. So reporting alone will not reduce the power used.
We suggest that the Malaysian government publish each data centre’s power report. The report should also name the power source: gas or renewable.
Tell us what you think
Should a data centre pay for power it reserves but does not use? Write to us. More in Intelligence. Related story: AI Data Centers and Carbon Emissions. New here? Read our Introduction.
Sources
- Bernama / Malay Mail, Malaysia to make data centre operators disclose power use, GPU imports under new law, says Johari Ghani, 12 November 2026.
- The Edge, Johari: New Law to Tighten Data Centre Oversight, Prevent Chip Transshipment, 13 November 2026.
- Malay Mail, As data centre power share heads for 21pc, Putrajaya moves to avoid phantom demand, 4 November 2026.
- New Straits Times, Data centre power demand in Peninsular Malaysia to surge to 31pct by 2035, 1 July 2026.
- The Star, Data centres account for 9.28% of total electricity consumption, 8 September 2026.
- The Vibes, Malaysia faces 9GW gas power gap as data centres drive electricity demand, 8 September 2026.